- Installation: First, lay the track, move the pedestal system, and install the walking device. Then, lift the bound steel keel into the pedestal, install the end formwork to fix the steel keel, and install the tie - rods to complete the formwork installation.
- Concreting: After the formwork is installed, pour the concrete into the formwork and vibrate it with a vibrator.
- Demoulding: After the concrete reaches the demoulding strength, remove the tie - rods at the top, start the hydraulic device to complete the demoulding, and then move the poured T - girder to the curing room for curing by using the movable pedestal.
Definition and Composition
- Definition: T - girder formwork is a special formwork used to pour T - girders in bridge construction. The main girder has a cross - section shape similar to the capital letter "T", so it is called "T - girder".
- Composition: It is usually composed of side formwork, bottom formwork, end formwork, etc. The side formwork is made of channel steel transverse ribs, panels, and I - steel support combinations. The bottom formwork is generally made of concrete, and the end formwork is made of steel ribs and panels. The three are connected by bolts.